As of 05/19/2024 07:20 AM AKDT
This report includes projects that we anticipate advertising in the next 12 months. Unless otherwise stated, plans and specifications are not available at this time. Please check out the Bid Calendar for projects currently advertising.
Click here to generate an Excel file of the report below.
Region(s):The scope of work for this federally funded contract includes the installation of a new Owner-Furnished Controlled Pitch Propeller (CPP) System on the M/V Columbia, including Alarm and Monitoring systems installation, Fire Detection system, testing, and demonstration of acceptable operation to regulatory agencies and the owner. Work includes necessary remediation of contaminated materials, limited engineering, documentation, and State funded annual overhaul work as outlined in the plans and specifications.
more >The project will repair unstable slopes from MP 3.0 to MP 3.9 on Tongass Highway.
more >Construct permanent repairs to the Kougarok Road at MP 61.5, MP 66.5, and MP 79.5. Project includes roadway reconstruction and drainage improvements.
more >Rehabilitate the Alaska Highway and construct new passing lanes. Project work will include bridge work, roadside hardware, drainage, intersection improvements and utilities.
more >Rehabilitate approximately 7,000 feet of the tug road from Taxiway Victor to Alaska Cargo Port. Project includes pavement planning, paving, and striping.
more >Install an estimated 70 monitors and 70 input stations with associated hardware, software, and accessories to provide visual paging throughout the South Terminal, Connector, and North Terminal Lobby to meet Americans with Disabilities Act (ADA) requirements.
more >This project will rehabilitate the runway, taxiway, apron, and airport access road. The runway safety area will be expanded, and runway grades will be corrected to meet line-of-sight requirements. Additional improvements include replacement of airfield lighting, FAA navaids, wind cones, segmented circle, build a supplemental wind cone access, and apply dust palliative.
more >This federally funded contract includes all necessary design and construction services as required to construct the replacement of a new apron drive passenger boarding bridge (PBB) at the Fairbanks International Airport, North Terminal, Gate 3.
more >This project will remove and replace the existing single bay SREB at the same location.
more >This federally funded contract will perform work at the Glenn Highway Kinik River bridges and Peters Creek bridge. Work includes bridge deck and expansion joint repair work, guardrail, and paving. Limited duration bridge closures to perform the work will require installation of temporary detours as well as use of a movable concrete barrier system for changing the number travel lanes available for peak daily traffic flow direction during closures.
more >Reconcile right of way and encroachment conflicts along the Glenn and Richardson Highways near Glennallen Alaska, to allow for completion of future federal projects. This work may include right of way research, appraisals, purchases and other activities necessary to eliminate conflicts. Completion of a highway wayside as part of the conflict elimination will also be included as part of this effort.
more >Construct fencing along the boat launch on the Gulkana River.
more >This HSIP project will construct a flashing beacon and load center at the intersection of Church Road and Spruce Ave. Work may include drainage improvements, roadside hardware, ADA improvements (curb ramp & pathway), and utilities.
more >The Kalsin Bay Maintenance Station was replaced in 2019. The reconstructed facility is a 4100 SQ. Ft. steel frame building with three maintenance bays and an adjoining office, break room, and bathroom. Phase 2 consists of miscellaneous remaining scope required for full functionality of the maintenance station, including but are not limited to, concrete apron replacement, building envelope upgrades, domestic water filtration, wastewater holding tank modifications, fuel tank relocation, provision of an emergency generator, and other mechanical and electrical upgrades.
more >Bridge strengthening to NBI#797 at the intersection of Bauer Way and Water Street.
more >Perform structural upgrades and replace Nenana DOT Maintenance Station shop roof.
more >Reconfigure existing parking lot and access roads at Pearl Creek Elementary School in Fairbanks in order to improve vehicle circulation and reduce vehicle idling. Parking lot work includes installation of new vehicle electrical plug-ins, ADA improvements, drainage improvements, paving, and roadside hardware.
more >This state funded project is to construct a storage building for the Plant Materials Center.
more >Construct a new three bay snow removal equipment building including space for lighting controls and backup generators and a new deicing material storage building.
more >Project will include constructing a new vehicle access control gate at AFM West and install head bolt outlets (HBO) at the TW A and DeHavilland Avenue snow disposal sites.
more >This project will design and construct improvements for the North Terminal Northside Aprons and Taxilane.
more >Install a vertical pivot gate to secure the M&O yard at the Old AFM complex and card reader at North Terminal Employee exit.
more >Rehabilitate Postmark Drive from Rockwell Avenue to Dehavilland Avenue. Project includes pavement planning, paving, striping, and drainage.
more >Provide a drainage system for the lighting duct near the east end of Runway (RW) 7L/25R.
more >Remove and replace approximately 1,000 feet of security fence along the northeast edge of the airfield. Project includes clearing, grubbing, embankment extension and replacing swing gates. To be advertised with CFAPT00880 ANC Taxiway R North and Taxilane U Improvements project.
more >This project will design and construct improvements for TW R from approximately TL P to TW Q for Airplane Design Group 6.
more >This federally funded project will rehabilitate approximately 6,000 feet of water pipe around the North Terminal, C Concourse, A Concourse, and Old Airfield Maintenance (OAM) building at the Ted Stevens Anchorage International Airport. Improvements will also include hydrant replacements, valve replacements, and grouting a decommissioned water pipe segment under the South Terminal. To be advertised with CFAPT00881 ANC NORTH TERMINAL NORTHSIDE APRONS & TAXILANE RECONSTRUCTION.
more >Reconstruct eleven signalized intersections at multiple locations in the City of Fairbanks. Work includes intersection improvements and roadside hardware.
more >Construct drainage improvements at the Deadhorse Airport and along Deadhorse Drive and fill in-fields adjacent to the runway and apron. Construct a wildlife perimeter fence with a service road around the airfield.
more >Reconstruction of Haines Highway from Milepost 20 to 25 including the Chilkat River bridge.
more >Replace failing culverts on the Hope Highway at MP 7.9 and MP 12.9. Additional improvements may include, as necessary, resurfacing, erosion protection, guardrail, signs, and striping.
more >Provide additional illumination at the Stedman/Deermount intersection to achieve a level of luminance that meets current DOT&PF standards. Construct a concrete sidewalk bulbout on the Stedman side of the marked crosswalk. The bulbout will extend from the existing sidewalk to the edge of the traveled way.
more >The work includes excavation, grading, chip seal, culvert replacement, seeding, rock armoring, and stream channel restoration.
more >The project includes highway milling and paving, guardrail replacement, culvert replacement and lining, grading, and striping.
more >Reconstruct seven signalized intersections at multiple locations in the Fairbanks and Parks Highway Nenana Canyon area. Work includes intersection improvements and roadside hardware.
more >Rehabilitate sections of the Shishmaref Sanitation Road and construct erosion control features. Project will include drainage improvements and roadside hardware.
more >Provide additional illumination at the Halibut Point Road/Peterson Avenue Intersection to achieve a level of luminance that meets current DOT&PF standards. Modify adjacent roadway lighting as needed to maintain satisfactory continuous illumination. Establish a pass-through crossing to facilitate less challenging pedestrian movements. Improve intersection sight distance by removing utility equipment located in the southeast quadrant of the intersection, acquiring property to remove parking spaces that, when occupied, create sight line obstructions, and modifying access to an apartment building adjacent to the intersection (shorten curb cut). Replace existing S1-1 School signs with W11-2 advance pedestrian warning signs.
more >This project is for Sitka Seawalk Stage II, which will continue the Sea Walk from the Sitka Public Library to the O¿Connell Lightering Facility. This project would improve pedestrian and ADA accessibility to the existing facilities.
more >Replace automated vehicle gate 3; Replace and widen vehicle gate 9 from 20' to 24'; Replace non-automated vehicle gate 10; Replace locking systems for vehicle gates 3 and 9; Replace locking systems for fence pedestrian gates 4 and 11; Remove vehicle gates 5 and 6 and replace with fence; Replace and relocate pedestrian gate 11; Repair approximately 1200-1500 feet of fence line.
more >Perform deferred maintenance on the active firing/shooting range at ANC by removing lead bullets and bullet fragments. Amend remaining affected soil with a heavy metal fixation reagent to prevent leaching of lead.
more >Replace runway and taxiway lighting systems, the segmented circle and lighted primary wind cone, and the lighted supplemental wind cone.
more >This project will construct permanent repairs (PR) to the upper & lower portion of the Waydelich Creek retaining wall. The upper wall was damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIR AK2021-1 JNS003. Repairs may include, but are not limited to, asphalt, embankment, geotextile, concrete, steel reinforcement, riprap, drainage, roadside hardware, and utilities. Phase code is T02015. The lower wall has years of deterioration & requires additional work to bring the full wall up to seismic code & extend the service life another 40 years. This portion of the project has PM-funding. Phase code is T02A15.
more >Project will replace/upgrade access controls and gates to meet 49 CFR 1542 requirements. Replace existing fencing when needed.
more >This project will rehabilitate the Kenai Spur Highway between Soldotna and Kenai. A 5-lane highway will be constructed between the Sports Lake Road and Robin Drive intersections to increase capacity and improve safety. This is the second of two phases to construct the project.
more >Culvert replacement, drainage improvements, ditch grading, guardrail, signage, utility relocations, clearing and grubbing. This Child Project will construct the first phase of improvements included in the Parent Project CFHWY00592. .
more >New bridge, drainage improvements, ditch grading, guardrail, signage, utility relocations, clearing and grubbing. This Child Project will construct the second phase of improvements included in the Parent Project CFHWY00592.
more >Realign and rehabilitate Seppala Drive in Nome. Work includes pavement rehabilitation, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Construct a perimeter road along the northwest edge of the security fence. The road will begin just south of the fuel farm and continue around northwest to follow the existing security fence. Project includes structural section, paving, and security fencing.
more >Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >This project will replace or rehabilitate the Sayles/Gorge Street Viaduct (#1841).
more >Rehabilitate the runway, taxiway, safety areas, apron, and access road. Widen and extend RSA to meet ADG II standards. Place and compact CASC, apply dust palliative. Reconstruct the airfield lighting system, primary wind cone, and supplemental wind cone. Replace rotating beacon on a tip-down pole. Relevel SREB. Construct barge landing.
more >This state funded emergency project will remove and replace the damaged girder on the Peters Creek Undercrossing (NBI 1367) on the Glenn Highway. Work also includes cast in place concrete, bridge rail, pavement striping, and traffic control.
more >Pavement preservation, which may include improvements to roadside hardware, drainage, intersections, automated traffic recorders, pedestrian facilities, bridge work, striping, and utilities.
more >This pavement preservation project includes resurfacing, roadside hardware, drainage improvements, bridge improvements, ADA improvements, and utilities as necessary.
more >Begin preliminary design for the Unalaska airport apron and taxiway rehabilitation. For the terminal apron: mill 2 inches of the existing AC pavement and repair underlying PCC. Repave with 2 inches hot mix asphalt. For the hanger apron: repair PCC surface and joints and overlay with 2 inches of hot mix asphalt.
more >Relocate the BLM Road to the Cambell Tract Facility 260 feet to align East 68th Avenue with intersection improvements to include bus stop and integration to existing signalized intersection.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for Disaster Inventory Numbers 461219, 461641, 548035, and 461258. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Mud Bay Road, Sawmill Road, and at the DOT&PF Maintenance Yard. This project is funded by FEMA.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIRs AK 2021 01 HNS00l, AK 2021 01 HNS002, AK 2021 01 HNS003, and AK 2021 01 HNS004. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Haines Highway.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIRs AK 2021 01 HNS005, AK 2021 01 HNS006, AK 2021 01 HNS007, AK 2021 01 HNS008, AK 2021 01 HNS009, AK 2021 01 HNS010, AK 2021 01 HNS011, and AK 2021 01 HNS012. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Haines Highway & Lutak Road.
more >This project will design and construct a chip seal overlay on Glacier Highway, between Brotherhood Bridge and the Auke Bay Roundabout.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIR AK 2021 01 JNU002, AK 2021 01 JNU004, AK 2021 01 JNU005, and AK 2021 01 JNU006. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Glacier Highway/Lemon Road, Egan Drive/Glacier Highway, and Glacier Highway/Twin Lakes Drive. This project is funded by FHWA.
more >Rehabilitate Ruby Slough Road from Ruby Slough to the landfill. Project will include drainage improvements and roadside hardware.
more >Pavement preservation, bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Project will construct a connection between the Tony Knowles Coastal Trail to the Ship Creek Trail in downtown Anchorage. Major Project Elements include Bridge Work (Pedestrian), Roadside Hardware, Drainage Improvements, Intersection Improvements and ADA Improvements.
more >Replace two damaged culverts with new Aquatic Organism Passage structures across Trout Creek and Little Trout Creek in Cold Bay, AK.
more >Reconstruct Cowles Street from Airport Way through East Cowles Street. Project work will include roadside hardware, drainage improvements, intersection improvements, ADA improvements and utilities.
more >Resurface the Glenn Highway between MP 143-154. Project includes bridge work, drainage improvements, pavement preservation, roadside hardware, and utilities.
more >The project will reconstruct the three-leg intersection of Palmer-Fishhook Rd and Trunk Rd. This project may also include roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Project to address remaining Asbestos ad HVac Issues within the Dot 7mi complex's main building within Juneau Alaska
more >Reconstruct Taxiways C and D at Kodiak Airport, Kodiak, AK. This new project replaces stages 2 and 3 of Kodiak Airport apron and Taxiways C, D, and F reconstruction.
more >Resurfacing and grading the runway, regrading ditches and safety areas, replacement of inoperative culverts and drainage repairs. Installation of new AWOS. CC 24300447 LC 33008462 Phase: T02FA1 LC & CC Description: SFAPT00361-2P-Resurf.
more >Reconstruct the Richardson Highway between MP 167 and 173. Project includes roadside hardware, drainage improvements and utility relocations.
more >Provide a design to improve the function, utilization, and maintenance of the C Concourse Plaza area.
more >Rehabilitate and extend the life of the aprons at Gates N2 and N4 to include joint seal replacement and concrete rehabilitation
more >Rehabilitate and extend the life of aprons RON 12, 13, and 14 to include joint seal replacement and concrete rehabilitation.
more >Adjust drive lanes at the entrance to provide enough width for maintenance equipment to plow in the vicinity of the access points. Project could include pavement removal and replacement, curb removal and replacement, landscaping, and utility relocations.
more >Rehabilitate Taxiway Echo from Taxiway Victor to Taxiway Lima. Improvements include: provide adequate typical section; evaluate taxiway safety area; replace lighting, markings, and signs; remove, replace, or modify existing storm drainage as needed; and adjust utilities as needed.
more >Rehabilitate approximately 5,000 feet of the Tug Road from Taxiway Alpha to A Concourse. Project includes, pavement rehabilitation, drainage improvements and pavement markings.
more >Resurface Chena Ridge Road and Chena Pump Road. Project will include bridge work, drainage improvements, embankment stabilization, and roadside hardware.
more >Signing and striping on paved Fairbanks city streets to designate space for seasonal bicycle use. Project will include ADA improvements.
more >Resurface the Glenn Highway from Kings River bridge to Cascade. Additional improvements may include bridge work, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities as necessary. Project construction may be phased.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for Damage Inventory Numbers 461220 - 461221, 461229, 461231 - 461236, 461253, 461255 - 461257, 461652, 784622, and 918887 - 918890. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Beach Road, Front Street, Allen-Menaker Road, Comstock Road, Piedad Road and Mud Bay Road. This project is funded by FEMA.
more >Rehabilitate the pavement of Aircraft and Lakeshore Dr from Voight Cir to the Lake Hood East property boundary south of runway 14/32. Project includes roadway reconditioning, structural section repairs, drainage improvements, and striping.
more >This pavement preservation project will resurface Old Glenn Hwy, Outer Springer Loop and Inner Springer Loop. Additional improvements may also include: utility relocation, roadsidehardward, vegetation clearing, dig-outs, drainage, signs, striping, bridge repairs, ADA improvements, and safety improvements.
more >Pavement Preservation of Palmer-Fishhook Road Mileposts 7-17 and may include, as necessary: Bridge Work, Roadside Hardware, Drainage Improvements, and Utilities.
more >Make improvements to the AMHS Auke Bay Terminal East Berth. Work would include: Replacement of mooring dolphins, refurbish/replace transfer bridge and support float, install mechanical and electrical upgrades.
more >Reconstruction, roadside hardware, drainage improvements, intersection improvements, ADA improvements, and utilities.
more >Reconstruct Miller Hill Road and Yankovich Road, and improve existing separated multi-use path as needed. Project work will include roadside hardware, drainage improvements, and utilities.
more >This project will construct additional aircraft parking at LHD Echo Parking to replace parking impacted by FAA's new ATCT.
more >Resurface the existing runway, taxiway and apron and provide drainage improvements. Upgrade lighting system and electrical building. Provide erosion protection for the runway safety area at Runway 29. Replace segmented circle. Upgrade and armor the airport access road to reduce flooding and provide cross drainage. Apply dust palliative to all airport operational surfaces and access road.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for Damage Inventory Numbers 461224, 461227, 461237 - 461239, 461243 - 461250, 784625 - 784632, and 786036. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites on Lutak Road. This project is funded by FEMA.
more >This project will install FYA signal heads for existing protected-permissive and permissive left turning movements (opposing left turns will both be upgraded, where identified); install new signal poles, mast arms, and foundations as required to complete FYA upgrades; upgrade existing TS-1 traffic controller cabinets and electrical load centers to support FYA operation; relocate mast arm signage and reconstruct existing sidewalk, roadway, curb and gutter, and curb ramps as required to modify the required traffic signal to FYA operation.
more >Construct a roundabout at the intersection of Chena Pump Road, Old Chena Ridge Road, and Chena Small Tracts Road. Project will include intersection improvements, roadside hardware, and utilities.
more >Construct a single-lane roundabout at the Loop Road - Mendenhall Boulevard - Valley Boulevard intersection.
more >Resurface the runway, taxiway, apron, and access road to correct deep cracks, uneven surfaces, soft spots, and areas where subbase is exposed. Replace lighting, NAVAIDS, and improve drainage.
more >Resurface Anchor Point Road from Old Sterling Highway to end of road at beach parking lot. This project will include: Pavement Preservation, Roadside Hardware, Drainage improvements, and Utilities.
more >Pavement Preservation of DeArmoun Rd. from East 140th Avenue to Hillside Drive including improvements to drainage, intersections, ADA, roadside hardware, and utilities. High Friction Surface Treatment may be reapplied.
more >Rehabilitate and construct safety improvements to the Kotzebue Airport crosswind runway 18-36 and taxiway G, replace airfield lighting, apply dust palliative, and construct a new general aviation apron.
more >This project will design and construct permanent repairs (PR) to assets damaged by the December 2020 Storm in the Southcoast Region of Alaska for DDIRs AK 2020 01 HNH001, AK 2020 01 HNH002, AK 2021 01 PTG002, AK 2021 01 PTG003, and AK 2021 01 SGY001. Repairs may include, but are not limited to, asphalt, embankment, geotextile, riprap, drainage, roadside hardware, retaining walls, and utilities. This project will repair sites in Hoonah, Petersburg & Skagway.
more >This project proposes to rehabilitate and resurface the operational surfaces at the Tununak Airport to correct cracks, ruts, uneven surfaces, dips (over 6"), soft spots, and ponding. Dust palliative will be applied for fines preservation to bind aggregate and prevent loss of fines. Drainage improvements may include special ditching and culvert realignment where needed. Lighting and visual aids will be repaired or replaced where they have been damaged or displaced by subsidence.